Superload Permits: Size, Weight and Route Checks

Material criteria and scheduling claims reviewed October 23, 2026 against the primary agency sources below. Different review levels and source-boundary ambiguities are identified explicitly.

A superload exceeds a state’s routine permit criteria and may require additional route, structure or movement review. Pennsylvania’s published definition includes loads over 201,000 pounds, over 160 feet long or over 16 feet wide. Check every dimension and the applicable permit category; there is no national threshold.

On This Page

This guide is written from the state regulations, and each number links to the rule it came from.

In one minute: your load becomes a superload when it passes a width, height, length or weight number written into that state's rules. Pass any one of them and the permit stops being routine.

Cross a state line and the number changes underneath you.

What is a superload?

A superload is a non-divisible load that exceeds the size or weight a state will permit routinely. The applicable process can include permit staff, bridge engineers, route surveys and special movement conditions. The criteria below identify different state categories; they are not interchangeable clearance limits.

Delaware writes the definition most plainly.

Regulation, verbatim

"Superload" means any vehicle or load is considered a SUPERLOAD when any one of the following conditions exist:

"15 feet or more in width; 15 feet or more in height; 120 feet or more in length; has a gross weight in excess of 120,000 lbs."

— 2 Del. Admin. Code 2405-3.0. Verified September 8, 2026.

Warning

Note the phrase "any one of the following". You do not need to pass all four numbers; one is enough.

Where does oversize end and superload begin?

Oversize begins at the federal width limit and superload begins wherever the state says. Under 23 CFR 658.15, no state may set a National Network width limit other than 102 inches, which is 8 feet 6 inches (8'6"). Above that you need a permit. Far above it, you need a reviewed one.

Selected Width References And Review Levels Selected width references: 8 feet 6 inches is the federal National Network width standard; Delaware lists a 15-foot superload width criterion; Georgia and Nebraska use over 16 feet. Virginia’s over-18-foot reference concerns an additional travel-plan requirement, not its complete superload definition. Other dimensions and conditions also apply. Load width, in feet Different review levels Oversize State review 8'6" federal 23 CFR 658.15 15' Delaware 16' GA, NE 18' VA plan
These references describe different review levels. Virginia’s over-18-foot marker concerns an additional travel plan; it is not a general boundary between ordinary and superload permits.
RouteAll app: turn the permit into a plan
RouteAll app view. Import your permit into RouteAll, review the extracted details and check the route before departure.

Which states call it a superload, and at what number?

Check width, height, length, gross weight, axle configuration and route together. The table distinguishes superload criteria from Virginia’s additional travel-plan parameters. A number that does not trigger one criterion can still require review under another.

Selected state superload criteria and additional review parameters; confirm the category and boundary with the issuer.
StateWidth or heightLength or weightSource
Delaware15 feet or more wide or high120 feet or longer; confirm the 120,000-pound boundary with DelDOT2 Del. Admin. Code 2405-3.0
GeorgiaOver 16 feet wide or high150,001–180,000 pounds; over 180,000 uses Superload PlusGa. Comp. R. & Regs. 672-2-.01
KansasNot stated by dimensionOver 150,000 pounds grossKan. Admin. Regs. 36-1-38
MissouriOver 16 feet wide or highOver 150 feet; over 160,000 pounds7 CSR 10-25.020(15)
NebraskaOver 16 feet wide or highOver 100 feet; over 160,000 pounds415 Neb. Admin. Code ch. 3, 001.27
PennsylvaniaOver 16 feet wideOver 160 feet long or over 201,000 pounds grossPennDOT M-936SLCA
Virginia — additional travel planOver 18 feet wide; over 16 feet highOver 200 feet; over 250,000 pounds24VAC20-82-60

Weight is only one part of the comparison.

Georgia is the one to read twice.

Warning

Do not classify a load by gross weight alone. Check every dimension, axle condition and permit category in each state before choosing the application process.

What does the state actually review?

Additional review may address bridge capacity, physical clearances, turns, traffic management and other route conditions. MoDOT’s current guidance describes a structure analysis and feasibility study for superloads, followed by a required route survey after the route is approved.

Regulation, verbatim

"Movers of superloads shall have a valid superload permit that includes a bridge analysis, which must be completed by the department before traveling on any highway within Kansas."

— Kan. Admin. Regs. 36-1-38. Verified September 8, 2026.

Other states describe the same review in their own words:

The analysis is what produces your route. The roads you are given are the roads the bridges allowed.

How much lead time do you need?

Allow for the issuer’s review process before committing a movement date. MoDOT’s May 2026 FAQ gives an approximate two-week turnaround, while Virginia asks for superload applications at least 10 working days before the move. These are planning references, not promised completion times.

Virginia also asks for a written travel plan on the largest moves. Per 24VAC20-82-60, movements over 18 feet wide, 250,000 pounds, 200 feet long or 16 feet high may have to submit one. The plan it describes is detailed.

Alabama coordinates law-enforcement escorts separately. ALEA’s current instructions require an ALDOT application and assigned reference number before scheduling. ALDOT’s superload information directs applicants to obtain permit-office pre-approval before contacting ALEA. Confirm both the permit and escort arrangements before travel.

Route detail matters more on a superload

For a superload, review the approved route together with its engineering instructions, surveys and movement conditions. Approval may depend on a specific configuration or crossing procedure. A detour can bypass the route that was reviewed, so resolve proposed changes with the issuer before travel.

Leaving the route is a different kind of mistake here than on a routine oversize move. Our guide on what happens if you leave your permitted route covers the general consequences.

If your load is nowhere near these numbers, start with do you need an oversize permit? The 4 numbers that decide instead. Escort requirements sit on a separate scale again, and are listed in pilot car requirements by state.

RouteAll reads the permit you already hold and follows the roads printed on it, which is the part that matters once an engineer has chosen them. How that works is on the RouteAll home page.

Use This Check In RouteAll

Use RouteAll’s manual permit review to check the route text against the issued document. Keep engineered crossing instructions, surveys and special approvals available separately. A plotted route cannot authorize a superload movement.

Superload checks before you roll

Find the superload threshold for every state on your route before you apply, not after. One state's routine oversize permit is another state's engineering review, and the review is what sets your schedule. Start with the state that has the lowest trigger on your lane. The RouteAll driver guides cover the permit side, and RouteAll support: report a permit the app read wrong takes those reports.

Common questions

Is there a federal definition of a superload?

No single federal superload threshold applies across the states. Pennsylvania’s published definition includes over 16 feet wide, over 160 feet long or over 201,000 pounds. Virginia’s higher travel-plan parameters are an additional review level, not its complete definition. Check the issuer’s criteria for the actual load.

How long does a superload permit take?

Timing depends on the load and required review. MoDOT’s May 2026 FAQ gives an approximate two-week turnaround; Virginia asks for applications at least 10 working days before the movement. Neither statement guarantees issuance by a chosen date.

Why does a superload need a bridge analysis?

Because the state has to know the structures will carry the load. The state may need to assess the structures on the proposed route. MoDOT describes structure analysis and feasibility review before issuance, with possible analysis charges. Clearance surveys and movement conditions remain separate requirements; the permit and its attachments govern.

Does RouteAll help with a superload permit?

Only after it is issued. RouteAll reads the permit you already hold and turns the roads written on it into navigation. It does not issue permits, apply for them, run a bridge analysis, or guarantee compliance. The driver remains responsible for the load.

Further reading

Sources

RouteAll reads the permit you provide. It does not issue permits or guarantee compliance. The driver remains responsible for the load. Rules change; verify against the permit and the issuing state before every move. This guide is written from published state regulations, not from operating experience with superloads.